POWERGRID Kala Amb Transmission Limited

(Location: Himachal Pradesh)
Project
Transmission system for Northern Region System Strengthening Scheme NRSS- XXXI (Part A)
Incorporation date
29 July 2013
TSA date
2 January 2014
Transmission license issue date
4 September 2014
Commercial Operation Date
July 2017
Remaining TSA tenure
28.28 years as on 31.03.2024
Gross block
INR 3,636 million as on 31.03.2024

Approval under Regulation 23 of CERC (Conduct of Business) Regulations,2023 for determination cum truing up of Transmission tariff for 2019-24 tariff block and determination of Transmission tariff for 2024-29 tariff block for Asset-1: 01 no. 420kV, 125 MVAr Bus Reactor alongwith associated bays at Kala Amb sub-station in Northern Region.
Transmission lines/Substations Location Line length / Transformation capacity Specifications Contribution to total transmission charges
LILO of both circuits of Karcham Wangtoo – Abdullapur transmission line at Kala Amb substation (on M/C towers) Himachal Pradesh 2.47 ckm 400 kV D/C 84.50%
400/220 kV GIS substation at Kala Amb Himachal Pradesh 630 MVA 400 kV / 220 kV GIS sub-station
40% Series compensation on 400 kV Karcham Wangtoo – Kala Amb (Quad) D/C line at Kala Amb ends Himachal Pradesh - 40% series compensation 15.50%